E.B. Campbell Hydroelectric Station completes refurbishment
SaskPower has now completed a major refurbishment at its E.B. Campbell Hydroelectric Station, north east of Tobin Lake.
The upgrades, which began construction in 2021, include improved turbines, generators, and intake systems.

(Image Credit: Ben Tompkins/northeastNOW)
“Specifically, the turbine made it more efficient, which means the same amount of water will actually get more output out of the units. We also replaced a lot of the main intake gates, which are where the water comes in from Tobin Lake, and modernized a lot of the control systems and actual control equipment in the basement, which actually operates the plant,” explained SaskPower Vice President of Engineering and Construction, Ryan Neufeld.