Paving project on Melfort’s Saskatchewan Drive entering last leg
Drivers travelling along Saskatchewan Drive in Melfort can soon expect a smooth ride.
Throughout the summer, the City of Melfort and their contractors have been working on preparing Saskatchewan Drive to be repaved. Now it’s finally ready. So far, sidewalks along the road have been replaced, water and sewer lines have also been replaced, as well as gutters and curbs being fixed or replaced.
According to Melfort’s Director of Development, Planning and Community Relations Brent Lutz, the contractor for the paving is expected to show up “late next week.” At that point, things will get going.
“The first part of the process will be milling the existing pavement where they remove a portion of that pavement before they apply the new pavement,” Lutz told northeastNOW. “That way they can kind of reshape the street so that it maintains the proper crown and drains properly.”