New Mosaic Stadium 54 per cent complete
The new $278-million Mosaic Stadium is now over the halfway mark of being finished.
The city revealed that approximately 54 per cent of the project is now done. This time next year, the venue will be substantially complete.
“A significant amount of progress has been made. It’s been an excellent spring and summer for construction,” said PCL Construction’s Sean Hamelin.
He explained crews have lost only a handful of days from weather, including not only rain but also smoke from northern wildfires. At times, the air quality was such that strenuous physical activity outdoors was not recommended.