Melfort landfill decommissioning nearing completion

Aug 21, 2026 | 2:46 PM

A long project for the City of Melfort is nearing the finish line. 

The city’s landfill decommissioning is close to completion. 

“The old landfill cell is in the final stages of decommissioning, with the contractor putting down the final layer of cover material over the exposed waste, in preparation for topsoil and seeding,” Director of Public Works Kalyna Cipywnyk told northeastNOW. “The project is scheduled to be fully complete by the end of August, weather dependent.” 

Cipywnyk said decommissioning a landfill site isn’t as easy as covering the site and walking away, with several environmental regulations that must be met first. That includes a ‘cap’ over the landfill that must be engineered and constructed to minimize infiltration of surface water into the garbage underneath, and containing existing leachate, the liquid that forms when precipitation moves through waste in a landfill. 

“For this project, our landfill cap was constructed of a half-metre thick layer of compacted clay material over the waste, with topsoil and a vegetation layer,” explained CIpywnyk. “The clay material was excavated on site and was compacted to a specific density to encapsulate the historical waste area.” 

The city will submit the required documents to the Ministry of Environment for review and approval before the cell is officially declared closed. 

Cipywnyk said the new landfill cell, leachate pond, and stormwater management facility are all substantially complete, apart from commissioning the leachate pumps. The city expects that portion of the work to be completed by early next month. 

“We have learned a lot about operating the new cell in the last six months since we accepted our first load of residential waste in February,” said Cipywnyk. “As more and more loads have been directed to the new cell, our operators have done an excellent job of keeping an eye on the types of loads and working to prevent any damage to the new liner.” 

The existing cell had reached the end of its design life, according to Cipywnyk, and the Ministry of Environment directed the city to close the cell to reduce the risk of environmental contamination and to comply with current regulations. The cell that is being decommissioned did not have a liner or a barrier between the waste and the ground of the pit.   

“The new cell has a fully engineered liner and leachate management system which meets the current regulation and greatly reduces the risk of environmental contamination,” Cipywnyk said.   

The change means that the drop-off areas for grain bags, tires, scrap metal, and clean wood have been relocated from the active waste zone to the access road, which has been widened to accommodate two-way traffic to the new cell. Updated maps and signage will be produced to help customers navigate the site.  

Cipywnyk said the project wouldn’t have happened without the Investing in Canadian Infrastructure Program Grant awarded back in 2022, and the provincial and federal government funding was vital for the decommissioning to proceed. She thanked all landfill customers and Melfort residents for their patience and cooperation during the process.  

The budget for the decommissioning portion of the project was $2.8 million, with 33 per cent covered by the provincial government and 33 per cent by the federal government through the ICIP grant. The City of Melfort funded the remaining 33 per cent. The new landfill cell, including construction, engineering, new signage, and more, costs $6 million, fully covered by the municipality.

–  